Facility Alteration Permits

The FAP process reviews all proposed construction and development to ensure work doesn't harm airport operations or infrastructure.

No construction or demolition work can be done at Edmonton International Airport or Villeneuve Airport without an approved permit, and any work found being conducted without an approved permit may be shut down.

What Work Needs A FAP?

Who Needs to Apply?

Submission Requirements

How to Apply

Questions

 

What Work Needs A FAP?

Any work that may impact existing airport infrastructure will require review by Edmonton Airports.

A FAP - Development permit is required for a new development, addition or major renovation to an existing building, change in use of a building in occupancy, site stripping or creation of a stock pile.  Edmonton Airports is the Authority Having Jurisdiction for development at EIA.

A FAP - Construction permit is required when changes or improvments are made to infrastructure owned by or leased from EIA at both Edmonton International and Villeneuve Airports. Leduc County (EIA) and Sturgeon County (Villeneuve) are the Authorities Having Jurisdcition for work under the Alberta Safety Code.  They will not provide approval without an approved FAP- Construction from EIA.

Contact Technical Services at 780-890-8582 for more information on the approval process or excluded developments.

 

Who Needs to Apply?

All parties, whether they are tenants on an Edmonton Airports site, an agent of the Airport, or a third party working on Airport lands need to apply. The Applicant may be the contractor doing the work, the corporation for whom the work is being done for, or an outside representative acting on behalf of the corporation.

If the Applicant is not the Owner of the property, you will have to provide the name and contact information of the Owner or Primary Lease Holder.

 

Submission Requirements

Authentication of drawings by a Professional

In general FAP applications will require drawings completed by a professional (engineer, architect or both) and the continued involvement of the professional in the inspection of construction as mandated by the Alberta Building Code, and/or Architects Act and/or the Engineering and Geosciences Professions Act of Alberta.  Both permit submissions and project record drawings are required to be authenticated.

To avoid processing delays ensure that applications are complete including drawings authenticated by the appropriate professional(s).  For further information, please contact Technical Services at 780 890 8582.

See APEGA's authentication standards here: APEGA Authentication Standards

See the Alberta Association of Architects' practice bulletin here: Practice Bulletin PB-15

 

How To Apply for a FAP

Fill out our online Application Form using these guest credentials:

Login: shpoint\FAPUser          Password: F@Puser

Make sure you provide all the required documents so as to not delay the processing of your application.  Most permits take five (5) working days to process, but complex projects or applications without propoer supporting documentation will take longer.

We do charge a fee to process FAPs, using PayPal as an easy and secure way to pay the fee.

Your PayPal payment confirmation number will be required on your application form. Our staff and agents need only provide a project number or responsibility centre on the application form.

Fee Structure - 

Project Value Permit Fee:

Greater than $1 million - $1500

$10,000 to $1 million - $500

Less than $10,000 - $75

 

You can now apply for Leduc County Building at the same time as your FAP!  Fill out the front page with all of the details, and then proceed to the appropriate view to review and submit your permits!  You fill out the information only once, and provide your drawings all at once!  Contact Technical Services at 780-890-8582 or 780-890-8433 for more details or email us at fap@flyeia.com.

Questions?

Contact Technical Services - Edmonton Airports

Phone: 780 890 8433
Email: FAP@flyeia.com